Montana cut the construction repose period to six years — and the covenant clock with it
Montana cut the construction repose period to six years — and the covenant clock with it
2026-09-15 · Montana · Legislation
What happened. One 2025 bill shortened two clocks that Montana associations depend on, and it cut the construction one by 40 percent.
The bill
Senate Bill 143, “Generally revise civil liability laws relating to statutes of limitations for certain actions,” introduced by Sen. G. Hertz and Sen. D. Fern, became Chapter 174, Laws of 2025. Signed April 17, 2025; effective October 1, 2025. It amended two sections of the Montana Code Annotated.1
Written instruments: eight years to six
§ 27-2-202(1) now reads that the period for commencing “an action on any contract, covenant, obligation, or liability founded on an instrument in writing is within 6 years.”2
Construction: ten years to six
§ 27-2-208(1) now bars an action for damages “resulting from or arising out of the design, planning, supervision, inspection, construction, or observation of construction of any improvement to real property” commenced “more than 6 years after completion.” Subsection (2) gives one extra year where the injury occurs “during the sixth year after the completion” — previously the tenth.3
“Completion” is defined in subsection (4)(a) as “that degree of completion at which the owner can utilize the improvement for the purpose for which it was intended or when a completion certificate is executed, whichever is earlier.” The clock runs from completion, not from discovery of the defect.
Why six years is a hard number, not a soft one
Montana treats construction repose as substantive immunity rather than a procedural deadline. In Atkinson v. City of Livingston, 2026 MT 21, decided February 10, 2026, the Supreme Court described § 27-2-208 as “a substantive grant of immunity that extinguishes liability once the repose period expires,” citing among other authority Association of Unit Owners of Deer Lodge Condominium v. Big Sky of Montana, Inc., 245 Mont. 64, 798 P.2d 1018 (1990).4
The same opinion closed the re-pleading route. The court looks to “the gravamen of the claim rather than the label attached”: “Claims styled as negligence and negligent misrepresentation do not avoid the repose when they arise out of construction-related governmental functions.” Atkinson applied the ten-year version, because the suit was filed in April 2024. Associations filing after October 1, 2025 face the six-year version and the same doctrine.
The condominium transition problem this creates
Association defect claims surface late by nature. Turnover from a declarant happens after completion; envelope, roof and drainage failures manifest later still; and a volunteer board often needs a full budget cycle to get an engineer's report in hand. Six years from substantial completion is a short runway for that sequence, and the earlier trigger — completion certificate or first beneficial use, whichever is earlier — can pull the start date back further than a board expects.
Practical consequence for a Montana condominium or townhome association:
- Find the completion date before you need it. Not the closing date, not the recording date — the certificate or first beneficial use. That date is the only one the statute cares about.
- Buildings completed in 2020 or 2021 are at or past the new outer limit. An association still weighing whether to pursue a known defect on those buildings is weighing a decision the statute may already have made.
- Move the transition audit earlier. A reserve study tells you what things cost; a transition or building-envelope review tells you whether anyone else is liable for them. The second one now has a deadline.
The second clock: covenant abandonment came in two years sooner
This is the connection that is easy to miss, because it runs through a cross-reference. § 70-17-210(2) ties the covenant-abandonment defence to “the prescribed period in 27-2-202” — the very subsection SB 143 cut from eight years to six.
So a Montana covenant now goes dormant two years earlier than it did before October 1, 2025. Pair that with House Bill 147, effective May 5, 2025, which defines “enforcement action” as enforcement “equally and consistently” applied “on all properties subject to the covenant over at least a 2-year period,” and the two 2025 changes point the same way: the standard for preserving a covenant went up while the window for losing it got shorter.
The same six-year period applies, on the face of the statute, to actions on the declaration itself and to written assessment obligations.
What is genuinely unsettled
SB 143's applicability section (Sec. 3) says the act applies to actions “on any contract, covenant, obligation, or liability founded on an instrument in writing that are filed on or after October 1, 2025.” That sentence speaks to written-instrument actions. Whether the shortened construction repose in § 27-2-208 reaches claims that accrued before October 1, 2025 is not resolved by the statute's text, and we found no Montana decision construing it. Treat that as an open question rather than an answer in either direction — and treat it as a reason to establish your completion dates now instead of assuming which version applies.
Related Montana HOA Topics
- Senate Bill 143 (2025), enrolled bill with strike-and-insert text — Chapter 174, Laws of 2025 (Montana Legislature document store) ↩
- Mont. Code Ann. § 27-2-202 — six-year period for actions on a written instrument (Montana Code Annotated, official) ↩
- Mont. Code Ann. § 27-2-208 — six-year construction statute of repose and the sixth-year extension (official) ↩
- Atkinson v. City of Livingston, 2026 MT 21 (DA 25-0285, Feb. 10, 2026), slip opinion — repose as substantive immunity (Montana Judicial Branch) ↩
Stay on top of Montana HOA law
Every week: new Montana legislation, court rulings, and regulatory developments affecting condos, planned communities, and property managers. Free.
No spam. Unsubscribe anytime.